MORTARA INSTRUMENT, INC.
Project Name: Mortara Instrument, Inc.
Address: Milwaukee, WI
Architect: the Consortium ae
Completion Date: May 2016
Project Description: Catalyst Construction was contacted by the Mortara Instrument Inc.’s Owner’s Representative, Michael DeMichele, in late Spring of 2015, to propose on a new project. Catalyst was selected based upon a competitive budget and fee proposal. During the preconstruction phase, Catalyst, working in coordination with the Owner’s Rep and Architect (the Consortium ae), developed multiple budgets, defined scopes of work and help manage the design to stay in line with the initial project budget. Upon receipt of the Construction Documents, Catalyst bid the project out to multiple subcontractors in every category, and delivered a final construction contract, under the anticipated budget. Construction began on the 63,000sf facility in September of 2015 and completed in April of 2016.
COMMERCIAL